Compute-Storage Decoupled Cluster Upgrade Guide (Rolling Upgrade)

Doris compute-storage decoupled clusters support rolling upgrades, which require no full downtime and minimize impact on upstream applications. This document describes the complete upgrade procedure for compute-storage decoupled mode, including pre-upgrade checks, per-component upgrade steps, and answers to frequently asked questions.

To upgrade a compute-storage integrated cluster, refer to Cluster Upgrade.

Version Numbering

Doris uses a three-part version number (for example, 3.0.3). Run the following SQL to check the current version:

MySQL [(none)]> select @@version_comment;
+----------------------------------------------------------+
| @@version_comment |
+----------------------------------------------------------+
| Doris version doris-3.0.3-rc03-43f06a5e26 (Cloud Mode) |
+----------------------------------------------------------+

The version number fields are as follows:

PositionMeaningExample
FirstMajor version3
SecondMinor version0
ThirdPatch version3
Fourth (optional)Emergency bug-fix release, indicating a critical defect in the patch version2.0.2.1

The Cloud Mode suffix in the version string indicates that the cluster is running in compute-storage decoupled mode. Clusters running in compute-storage integrated mode do not have this suffix.

Mode switching restriction: Switching between compute-storage decoupled mode and compute-storage integrated mode is not supported.

Downgrade restriction: Upgrading from a lower version to a higher version is supported, and patch-version downgrades are supported. Minor-version and major-version downgrades are not supported.

Prerequisites

Before upgrading, confirm that all of the following conditions are met:

  1. Confirm the deployment mode: Verify that the cluster is running in compute-storage decoupled mode (the version string contains the Cloud Mode suffix).
  2. Configure import retry: Ensure that import jobs have a retry mechanism to prevent job failures caused by node restarts during the upgrade.
  3. Check component status: Verify that MetaService, Recycler, FE, and BE are all running normally with no error logs.
  4. Back up FE metadata: Back up the metadata directory of the Master FE (default: the doris-meta directory under the FE directory). If that directory is empty, check the meta_dir configuration item in conf/fe.conf for the actual path.
  5. Download the installation package: Download the target-version installation package from the Doris official website and verify the SHA-512 checksum to ensure package integrity.

Upgrade Process Overview

Upgrade each component in the following order:

  1. Upgrade MetaService
  2. Upgrade Recycler (only if deployed separately)
  3. Upgrade BE
  4. Upgrade FE
    1. Upgrade Observer FE nodes first
    2. Then upgrade other non-Master FE nodes
    3. Finally upgrade the Master FE node

Upgrade Steps

Step 1: Upgrade MetaService

Perform the following operations on each MetaService instance. Environment variables used in this step:

VariableMeaning
${MS_HOME}Working directory of MetaService
${MS_PACKAGE_DIR}Directory containing the new MetaService installation package

1. Stop the current MetaService

cd ${MS_HOME}
sh bin/stop.sh

2. Back up the existing binaries

mv ${MS_HOME}/bin bin_backup_$(date +%Y%m%d_%H%M%S)
mv ${MS_HOME}/lib lib_backup_$(date +%Y%m%d_%H%M%S)

3. Deploy the new installation package

cp ${MS_PACKAGE_DIR}/bin ${MS_HOME}/bin
cp ${MS_PACKAGE_DIR}/lib ${MS_HOME}/lib

4. Start the new MetaService

sh ${MS_HOME}/bin/start.sh --daemon

5. Verify the upgrade

Confirm that the MetaService process is running normally and that the new version number appears in ${MS_HOME}/log/doris_cloud.out.


Step 2: Upgrade Recycler (If Applicable)

caution

If the Recycler component is not deployed separately, skip this step.

Perform the following operations on each Recycler instance. MetaService and Recycler share the same installation package. Environment variables used in this step:

VariableMeaning
${RECYCLER_HOME}Working directory of Recycler
${MS_PACKAGE_DIR}Directory containing the new installation package (shared with MetaService)

1. Stop the current Recycler

cd ${RECYCLER_HOME}
sh bin/stop.sh

2. Back up the existing binaries

mv ${RECYCLER_HOME}/bin bin_backup_$(date +%Y%m%d_%H%M%S)
mv ${RECYCLER_HOME}/lib lib_backup_$(date +%Y%m%d_%H%M%S)

3. Deploy the new installation package

cp ${MS_PACKAGE_DIR}/bin ${RECYCLER_HOME}/bin
cp ${MS_PACKAGE_DIR}/lib ${RECYCLER_HOME}/lib

4. Start the new Recycler

sh ${RECYCLER_HOME}/bin/start.sh --recycler --daemon

5. Verify the upgrade

Confirm that the Recycler process is running normally and that the new version number appears in ${RECYCLER_HOME}/log/doris_cloud.out.


Step 3: Upgrade BE

tip

Before upgrading BE, confirm that all MetaService and Recycler (if applicable) instances have been upgraded.

Perform the following operations on each BE instance. Environment variables used in this step:

VariableMeaning
${BE_HOME}Working directory of BE
${BE_PACKAGE_DIR}Directory containing the new BE installation package

1. Stop the current BE

cd ${BE_HOME}
sh bin/stop_be.sh

2. Back up the existing binaries

mv ${BE_HOME}/bin bin_backup_$(date +%Y%m%d_%H%M%S)
mv ${BE_HOME}/lib lib_backup_$(date +%Y%m%d_%H%M%S)

3. Deploy the new installation package

cp ${BE_PACKAGE_DIR}/bin ${BE_HOME}/bin
cp ${BE_PACKAGE_DIR}/lib ${BE_HOME}/lib

4. Start the new BE

sh ${BE_HOME}/bin/start_be.sh --daemon

5. Verify the upgrade

Run the following SQL to confirm the BE version and status:

show backends;

Step 4: Upgrade FE

tip

Before upgrading FE, confirm that all BE instances have been upgraded.

FE nodes must be upgraded one at a time in the following order: Observer -> non-Master -> Master.

Perform the following operations on each FE instance. Environment variables used in this step:

VariableMeaning
${FE_HOME}Working directory of FE
${FE_PACKAGE_DIR}Directory containing the new FE installation package

1. Stop the current FE

cd ${FE_HOME}
sh bin/stop_fe.sh

2. Back up the existing binaries

mv ${FE_HOME}/bin bin_backup_$(date +%Y%m%d_%H%M%S)
mv ${FE_HOME}/lib lib_backup_$(date +%Y%m%d_%H%M%S)

3. Deploy the new installation package

cp ${FE_PACKAGE_DIR}/bin ${FE_HOME}/bin
cp ${FE_PACKAGE_DIR}/lib ${FE_HOME}/lib

4. Start the new FE

sh ${FE_HOME}/bin/start_fe.sh --daemon

5. Verify the upgrade

Run the following SQL to confirm the FE version and status:

show frontends;

FAQ

Q1: When upgrading a compute-storage integrated cluster, replica rebalancing must be disabled before the upgrade. Is this also required for compute-storage decoupled mode?

No. In compute-storage decoupled mode, Doris stores data on HDFS or object storage (S3), so there is no replica rebalancing requirement. This operation is not needed.

Q2: Given that MetaService provides a dedicated metadata service, why does FE metadata still need to be backed up?

Currently, metadata is maintained jointly by MetaService and FE, with each responsible for different parts. To ensure upgrade safety, back up the FE metadata directory before upgrading.